ENERGY: UAE TO JOIN GULF GRID BEFORE SCHEDULE
(ANSAmed) - ABU DHABI, JUNE 20 - The UAE has stepped up its
plans to join the Gulf Cooperation Council's (GCC) power grid
before schedule, senior officials told Gulf News.
The board of directors of the GCC Interconnection Authority,
which was established in 2001 to carry out the project, met in
the capital yesterday to approve the increase and restructuring
of the project's capital.
"We have agreed to increase the capital allocated for the
first phase of the project from $869 million to $1.212 billion,
while maintaining the original shares of the members relative to
the total," Yousuf A. Janahi, the authority's chairman told
Gulf News. "The original studies submitted in the late 1980s
and early 1990s estimated the project's investment cost at $3.3
billion, while the actual costs turned out to be only a third of
this assessment, which meant that we do not need any loans and
thus the restructuring of the project's financials to rely
totally on the available funds," he said.
The project timeframe divides the construction process into
three phases, first of which is the interconnection between the
northern countries; namely Saudi Arabia, Kuwait, Qatar, and
Bahrain.
The interconnection between the UAE and Oman comprises the
second phase, while in the third phase the whole grid will be
connected.
"The UAE was only supposed to join the grid after
accomplishing the interconnection with Oman, and the reason was
that the country's grid was far from the borders of the Northern
countries," Saeed Alo Darmaki, member of the authority's board
and deputy director of Transco, said. "We have already
proceeded with the preliminary works for establishing the border
sub-station at Al Selà a to be linked with Al Salwa sub-station
in Saudi Arabia, as well as the necessary cable towers," he
said. Construction is on schedule with the exception of the
marine cable of the first phase, as the actual geography of the
sea bed differed from that outlined in the studies. (ANSAmed).
2008-06-20 18:10